Brazil's Usiminas to stop Ipatinga No3 blast furnace for maintenance in July

By Ana Paula Camargo / March 12, 2018 / www.metalbulletin.com / Article Link

Brazilian flat steel producer Usiminas will carry out planned maintenance work on the No3 blast furnace at its Ipatinga works, in the country's south-eastern Minas Gerais state, after the restart of the No1 unit in April.

The outage was decided for the replacement of the equipment's staves, and is scheduled to last 14 days starting sometime in July, the mill told Metal Bulletin on Friday March 9."This is a common stoppage and will not affect the company's ability to...

Recent News

Gold stocks propelled by gain in metal and equities

May 13, 2024 / www.canadianminingreport.com

Big Gold producers report strong Q1/24 results

May 13, 2024 / www.canadianminingreport.com

Gold stocks decline as metal drop offsets equity risk on

May 06, 2024 / www.canadianminingreport.com

Canadian mining equity capital raising robust in 2023, early 2024

May 06, 2024 / www.canadianminingreport.com

Gold stocks gain even as metal price pulls back

April 29, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok