(IDEX Online) - The processing plant at Firestone Diamonds' Liqhobong Mine in Lesotho is operating again after the installation of temporary generators. The generators were brought in when the grid power supply to the mine was cut because of a planned shutdown at the Muela hydropower station

Firestone said the processing plant is operating at between 80-90-percent of full capacity. 

The generators are expected to be used until grid power is restored from Muela, which, according to the Lesotho Electricity Company, is scheduled to take place on 1 December. 

The mining company said normal operating costs are expected to increase by the cost of renting the gensets and of the associated diesel consumption.

Recent News

Gold stocks propelled by gain in metal and equities

May 13, 2024 / www.canadianminingreport.com

Big Gold producers report strong Q1/24 results

May 13, 2024 / www.canadianminingreport.com

Gold stocks decline as metal drop offsets equity risk on

May 06, 2024 / www.canadianminingreport.com

Canadian mining equity capital raising robust in 2023, early 2024

May 06, 2024 / www.canadianminingreport.com

Gold stocks gain even as metal price pulls back

April 29, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok