Company Press Releases

Kamoa-Kakula Phase 1 Concentrator Mills Approximately 320,000 Tonnes of Ore Grading 6.0% Copper in September, Exceeding Steady-State Design Throughput

2021-09-30 / @newsfile

A record 16,010 tonnes of copper produced in the month ended September 20More than 46,750 tonnes of copper produced year-to-date to September 202021 production guidance range for copper in concentrate raised to 85,000 to 95,000 tonnesFloated concentrate grade improved to 55.7% copper; average plant...Read More

Kamoa-Kakula Phase 1 Concentrator Plant Approaching Steady-State-Design Performance

2021-09-07 / @newsfile

14,815 tonnes of copper produced in August, bringing the year-to-date production to more than 36,700 tonnesInstallation of an additional concentrate filter expected by end of October 2021, further boosting copper productionPhase 2 concentrator plant construction now 44% completeMining crews delivere...Read More

Kamoa Copper Extends Existing Financing Agreement with DRC's State-Owned Power Company to Facilitate the Upgrade of Turbine 5 at the Inga II Hydropower Complex

2021-08-16 / @newsfile

Turbine 5 to produce 162 MW of renewable hydropower, providing the Kamoa-Kakula Copper Complex and associated smelter with sustainable electricity for Phase 3 and future expansionsCombined 240 MW output from the Mwadingusha and Inga II hydropower plants also will benefit local communities Kinshasa,...Read More

Ivanhoe Mines Issues Q2 Financial Results and Review of Operations, Mine Construction and Exploration Progress

2021-08-11 / @newsfile

Kamoa-Kakula Copper Mine achieved Phase 1 commercial production on July 1, 2021; first phase projected to produce approximately 200,000 tonnes of copper per yearKamoa-Kakula's Phase 2 expansion, scheduled for Q3 2022, will double annual copper output to approximately 400,000 tonnesIvanhoe Mines pled...Read More

Kamoa-Kakula Phase 1 Concentrator Plant Achieved Commercial Production On July 1, 2021

2021-08-03 / @newsfile

Copper production exceeded 500 tonnes per day towards the end of JulyPhase 1 concentrator copper recoveries averaged approximately 81% during July as commissioning advancesPhase 2 concentrator expansion to 7.6 Mtpa more than 35% complete; well on track to begin operations in Q3 2022Mining crews...Read More

Kamoa-Kakula Begins Exporting Copper Concentrate Internationally as Production Ramps Up

2021-07-19 / @newsfile

Kamoa Copper draws down US$300 million advance payment facility available under the offtake agreements; all future Phase 1 operating costs and majority of Phase 2 capital expenditures expected to be funded from copper sales and facilities in placeDaily shipments of copper concentrate to local smelte...Read More

Kamoa-Kakula Phase 1 Concentrator Plant Fully Operational; Hot Commissioning Activities Well-advanced, Final Performance Testing to Start Shortly

2021-07-06 / @newsfile

First truckloads of copper concentrate delivered to local smelter on June 1; daily concentrate deliveries ongoing, first blister copper ingots receivedPhase 2 concentrator expansion to 7.6Mtpa on track for Q3 2022; civil works and structural steel construction ahead of scheduleKamoa Copper fully aut...Read More

Kamoa-Kakula Monthly Progress Update Expected on July 6

2021-06-30 / @newsfile

Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - June 30, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) announced today that the June progress update for the Kamoa-Kakula Copper Mine in the Democratic Republic of Congo (DRC) is expected to be issued on July 6, 2021, after the major Canadia...Read More

Ivanhoe Mines Announces Results of Voting for the Election of Directors

2021-06-29 / @newsfile

Vancouver, British Columbia--(Newsfile Corp. - June 29, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) announced the results of voting by shareholders for the election of the Board of Directors during the company's Annual General Meeting held earlier today. The nominees listed in the management pro...Read More

Kamoa-Kakula's Off-Take Agreements Signed for Phase 1 Blister Copper and Copper Concentrate

2021-06-09 / @newsfile

Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - June 9, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng "Miles" Sun are pleased to announce that Kamoa Copper SA - the operating company of the joint venture between Ivanhoe Mines, Zijin Mining Group, Crys...Read More

Ivanhoe Mines Issues Fourth Annual Sustainability Report Showcasing the Company's Achievements Toward Becoming a Global ESG Leader in Mining

2021-06-08 / @newsfile

Vancouver, British Columbia--(Newsfile Corp. - June 8, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) announced today the publication of its fourth annual Sustainability Report.The report highlights Ivanhoe Mines' sustainability programs and initiatives in 2020, including significant accompli...Read More

Ivanhoe Mines Reports Fatality at the Kamoa-Kakula Copper Project

2021-06-04 / @newsfile

Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - June 4, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) regrets to report that a fatal accident occurred at the Kamoa-Kakula Copper Project in the Democratic Republic of Congo (DRC).The accident occurred underground at the Kakula Mine when a c...Read More

Kamoa-Kakula Phase 1 Concentrator Plant Produced First Copper Concentrate on May 25; Ramp Up Toward Nameplate Capacity of 3.8 Million Tonnes of Ore per Year Progressing Smoothly

2021-06-02 / @newsfile

First copper concentrates shipped to nearby Lualaba Copper SmelterMining crews deliver 406,000 tonnes of ore grading 5.77% copper in May, including 103,000 tonnes grading 8.58% copper from the centre of the Kakula Mine71,000 tonnes of ore grading 4.07% copper delivered directly from Kakula Mine to t...Read More

Kamoa-Kakula Monthly Progress Update Expected on June 2

2021-06-01 / @newsfile

Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - June 1, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) announced today that the May progress update for the Kamoa-Kakula Copper Project in the Democratic Republic of Congo (DRC) is expected to be issued on June 2, 2021.The Kamoa-Kakula Phase...Read More

Ivanhoe Mines Responds to Media Reports Regarding Copper Concentrate Exports from the Democratic Republic of Congo

2021-05-28 / @newsfile

Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - May 28, 2021) -  Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) is responding today to a media report stating that miners in the Democratic Republic of Congo (DRC) received an order on May 26, 2021 that has banned the export of copper and cobalt...Read More

Ivanhoe Mines Begins New Era of Commercial Copper Production

2021-05-26 / @newsfile

Kamoa-Kakula discovery enters production after 24 years of dedicated exploration and development effortsDemocratic Republic of Congo's President Félix Tshisekedi congratulates Ivanhoe for reaching the production milestone at the world-class discoveryPhase 2 concentrator expansion continues ahea...Read More

Ivanhoe Mines Issues Q1 Financial Results and Review of Mine Construction Progress and Exploration Activities

2021-05-13 / @newsfile

Copper production at the Kamoa-Kakula Mine to begin imminently; first phase projected to produce approximately 200,000 tonnes of copper per yearKamoa-Kakula's Phase 2 expansion, scheduled for Q3 2022, will double annual copper output to approximately 400,000 tonnesIvanhoe Mines pledges net-zero gree...Read More

Ivanhoe Mines Announces Inclusion in the MSCI Canada Index

2021-05-12 / @newsfile

Toronto, Ontario--(Newsfile Corp. - May 12, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) President and CFO Marna Cloete is pleased to announce the company has been informed that effective following the close of May 27, 2021, the Class A common shares of Ivanhoe Mines will be added to the MSCI Can...Read More

Ivanhoe Mines Pledges Net-zero Greenhouse Gas Emissions at the Kamoa-Kakula Copper Mine

2021-05-05 / @newsfile

London, England--(Newsfile Corp. - May 5, 2021) - Robert Friedland, Ivanhoe Mines’ Executive Co-Chair, announced today that Ivanhoe Mines has pledged to achieve net-zero operational greenhouse gas emissions (Scope 1 and 2) at the industry-leading Kamoa-Kakula Copper Mine in the Democratic Repu...Read More

Kamoa-Kakula to Begin Copper Production Within a Month

2021-05-03 / @newsfile

Mining crews deliver a record 409,000 tonnes of ore grading 5.71% copper in April, including 121,000 tonnes grading 8.40% copper from the centre of the Kakula MinePre-production ore stockpiles now hold three million tonnes grading 4.74% copper, containing more than 140,000 tonnes of copperKamoa-Kaku...Read More